1. Bucuresti-Ploiesti: in constructie, dare in exploatare primavara 2012, finalizare final 2012
Lot 1: 19,5 km Bucuresti-Moara Vlasiei | Constructor: Pizzaroti-Tirrena Scavi
Lot 2: 42,5 km Moara Vlasiei-Ploiesti | Constructor: Spedition UMB-PA&CO-Euroconstruct
In total: 62 km.
2. Ploiesti-Comarnic: fara finantare, fara noutati
In total: 49,6 km.
3. Comarnic-Brasov: fara finantare, se doreste PPP
In total: 55 km.
4. Brasov-Bors | "Autostrada Transilvania" in constructie, pe sectiuni
Lot 1A: 53 km Brasov-Fagaras | fara finantare, se doreste PPP
Lot 1B: 52 km Fagaras-Sighisoara | fara finantare, se doreste PPP
Lot 1C: 56 km Sighisoara-Targu Mures | fara finantare, se doreste PPP
Lot 2A: 36 km Targu Mures-Campia Turzii | se doreste finantare de la buget, se doreste licitarea lui in curand (2012)
Lot 2B: 52 km Campia Turzii-Gilau (Cluj Vest) | operational si finalizat
Lot 3A: 25 km Gilau-Mihaiesti | Gilau-Nadaselu se doreste finantare de la buget, trebuie licitat (2012)
Lot 3B: 76 km Mihaiesti-Suplacu de Barcau | fara finantare, fara noutati
Lot 3C: 64 km Suplacu de Barcau-Bors | in constructie, dare in exploatare 2013-2014 | Constructor: Bechtel
In total: 416 km.
----------------------------------------------------------------
TOTAL
- lungime totala: 580,6 km
- operational: 52 km
- operational nou in 2012: Bucuresti-Ploiesti
- operational nou in 2012: posibil un segment din Autostrada Transilvania 3C
- operational nou in 2013: Suplacu de Barcau-Bors
Vesti imbucuratoare despre segmentul Bucuresti Ploiesti ce se va inaugura din cate se pare pe 30 iunie cu o plimbare dedicata biciclistilor si pe 1iulie pentru traficul auto > http://www.skyscrape...569067&page=421
PS : Daca se respecta termenul, eu voi da o tura cu bicicleta pe 30 iunie !